Brief about the Project:

The Poultry project is strategic for Wi-sys and Awqaf and Wi-sys team will implement this project using latest SAP technology S4HANA which is the first implementation in the regain.

Project organization chart ( Project team):

Project scope:

Poultry – Al Qssaim

  • Simple Finance
  • FI-CO
  • Simple Logistics
    ◦PP
    ◦MM
    ◦SD
    ◦QM


Target audiences:

Poultry Team and Poultry Management

Project Plan (Timeline of the project):

  • Prepare: Jul 2016
  • Explore: Aug – Nov 16
  • Realize: Dec 16 – Feb 17
  • Deploy: Mar 17
  • Support: Apr 17 – May 17

Wi-sys partner in the project:

Wi-Sys team will implement this project.

Lesson learned:

N/A

Project output:

  • Best Practice of business processes
  • Real-time information system
  • Integrated solution between business entities